Skip to content

5.2 Pre-Deployment Checklist

Document Information

  • Version: 1.0
  • Last Updated: December 2025
  • Author: Abhavtech Network Engineering
  • Classification: Internal Use

5.2.1 Infrastructure Prerequisites

Network Infrastructure Checklist

Category Item Status Owner Verification
Connectivity Internet circuits at all sites ☐ ISP Team Bandwidth test
MPLS circuits operational (parallel) ☐ WAN Team Route verification
LTE/5G backup circuits ☐ Mobile Team Failover test
Out-of-band management network ☐ NOC Console access
IP Addressing Management IP ranges allocated ☐ IPAM Team Infoblox verify
Transport IP ranges allocated ☐ IPAM Team No conflicts
Service VPN IP ranges allocated ☐ IPAM Team VPN mapping
NAT pool ranges allocated ☐ IPAM Team DIA NAT
DNS SD-WAN Manager FQDN ☐ DNS Team Resolution test
SD-WAN Controller FQDNs ☐ DNS Team Resolution test
SD-WAN Validator FQDNs ☐ DNS Team Resolution test
Firewall Control plane ports (12346, 12446) ☐ Security ACL verify
Management ports (443, 8443) ☐ Security Access test
BFD ports (12386) ☐ Security UDP permit

IP Address Allocation Summary

+------------------------------------------------------------------+
|                IP ADDRESS ALLOCATION - ABHAVTECH                  |
+------------------------------------------------------------------+

MANAGEMENT NETWORK (VPN 512):
┌─────────────────────────────────────────────────────────────────┐
│  SD-WAN Manager Cluster:    10.255.0.0/24                       │
│    - sdwan-mgr-1:           10.255.0.11                         │
│    - sdwan-mgr-2:           10.255.0.12                         │
│    - sdwan-mgr-3:           10.255.0.13                         │
│    - Cluster VIP:           10.255.0.10                         │
│                                                                  │
│  SD-WAN Controllers:        10.255.1.0/24                       │
│    - vsmart-mumbai-1:       10.255.1.11                         │
│    - vsmart-mumbai-2:       10.255.1.12                         │
│    - vsmart-chennai-1:      10.255.1.21                         │
│    - vsmart-chennai-2:      10.255.1.22                         │
│                                                                  │
│  WAN Edge Management:       10.255.10.0/24 - 10.255.19.0/24     │
│    - Mumbai:                10.255.10.0/24                       │
│    - Chennai:               10.255.11.0/24                       │
│    - Bangalore:             10.255.12.0/24                       │
│    - Delhi:                 10.255.13.0/24                       │
│    - Noida:                 10.255.14.0/24                       │
│    - London:                10.255.15.0/24                       │
│    - Frankfurt:             10.255.16.0/24                       │
│    - New Jersey:            10.255.17.0/24                       │
│    - Dallas:                10.255.18.0/24                       │
└─────────────────────────────────────────────────────────────────┘

TRANSPORT NETWORK (VPN 0):
┌─────────────────────────────────────────────────────────────────┐
│  System IPs (TLOC):         10.255.255.0/24                     │
│    - Mumbai Hub-1:          10.255.255.1                        │
│    - Mumbai Hub-2:          10.255.255.2                        │
│    - Chennai Hub-1:         10.255.255.3                        │
│    - Chennai Hub-2:         10.255.255.4                        │
│    - Bangalore:             10.255.255.11                       │
│    - Delhi:                 10.255.255.12                       │
│    - Noida:                 10.255.255.13                       │
│    - London:                10.255.255.21                       │
│    - Frankfurt:             10.255.255.22                       │
│    - New Jersey:            10.255.255.31                       │
│    - Dallas:                10.255.255.32                       │
│                                                                  │
│  Transport Interfaces:      Assigned by ISP (public)            │
└─────────────────────────────────────────────────────────────────┘

SERVICE VPNs:
┌─────────────────────────────────────────────────────────────────┐
│  VPN 10 (Employee):         10.10.0.0/16                        │
│  VPN 20 (Guest):            10.20.0.0/16                        │
│  VPN 30 (IoT):              10.30.0.0/16                        │
│  VPN 40 (Voice):            10.40.0.0/16                        │
│  VPN 50 (Shared Services):  10.50.0.0/16                        │
│  VPN 100 (PCI):             10.100.0.0/16                       │
└─────────────────────────────────────────────────────────────────┘

5.2.2 Hardware Prerequisites

Controller Hardware

Component Specification Quantity Status
SD-WAN Manager
vCPU 32 cores 3 VMs ☐
Memory 64 GB 3 VMs ☐
Storage 1 TB SSD 3 VMs ☐
Network 10 Gbps 3 VMs ☐
SD-WAN Controller
vCPU 8 cores 4 VMs ☐
Memory 16 GB 4 VMs ☐
Storage 100 GB 4 VMs ☐
Network 1 Gbps 4 VMs ☐

WAN Edge Hardware

Site Model Quantity Interfaces Status
Mumbai DC C8500-12X4QC 2 12x10G, 4x100G ☐ Staged
Chennai DR C8500-12X4QC 2 12x10G, 4x100G ☐ Staged
London C8300-2N2S-6T 2 2xNIM, 6x1G ☐ Shipped
Frankfurt C8300-2N2S-6T 2 2xNIM, 6x1G ☐ Shipped
New Jersey C8300-2N2S-6T 2 2xNIM, 6x1G ☐ Shipped
Dallas C8300-2N2S-6T 2 2xNIM, 6x1G ☐ Shipped
Bangalore C8300-1N1S-6T 2 1xNIM, 6x1G ☐ Ordered
Delhi C8300-1N1S-6T 2 1xNIM, 6x1G ☐ Ordered
Noida C8300-1N1S-6T 2 1xNIM, 6x1G ☐ Ordered

Hardware Verification Checklist

#!/bin/bash
# hardware_verification.sh - Pre-deployment hardware check

echo "=== ABHAVTECH SD-WAN HARDWARE VERIFICATION ==="

# Check serial numbers against purchase order
echo "Step 1: Serial Number Verification"
cat << 'EOF'
Site: Mumbai DC
  Router 1: FCW2534L0AB (Expected: FCW2534L0AB) [MATCH]
  Router 2: FCW2534L0AC (Expected: FCW2534L0AC) [MATCH]
EOF

# Verify firmware versions
echo "Step 2: Firmware Version Check"
cat << 'EOF'
Minimum IOS-XE: 17.15.1a
  Mumbai-1: 17.15.1a [OK]
  Mumbai-2: 17.15.1a [OK]
EOF

# Check licenses
echo "Step 3: License Verification"
cat << 'EOF'
Required: DNA Advantage
  Mumbai-1: DNA-A-P-25G [OK]
  Mumbai-2: DNA-A-P-25G [OK]
EOF

5.2.3 Software Prerequisites

Software Versions

Component Required Version Status Download Location
SD-WAN Manager 20.15.1 ☐ software.cisco.com
SD-WAN Controller 20.15.1 ☐ software.cisco.com
SD-WAN Validator 20.15.1 ☐ software.cisco.com
WAN Edge IOS-XE 17.15.1a ☐ software.cisco.com

License Requirements

License Type Quantity Term Status
DNA Advantage - 25G 4 5 years ☐ Ordered
DNA Advantage - 10G 8 5 years ☐ Ordered
DNA Advantage - 1G 6 5 years ☐ Ordered
SD-WAN Controller 4 Perpetual ☐ Included
SD-WAN Manager 1 Perpetual ☐ Included
Security Bundle 18 5 years ☐ Ordered
Umbrella SIG 500 users 5 years ☐ Ordered

5.2.4 Security Prerequisites

Certificate Requirements

Certificate Type Purpose Status
Root CA Enterprise CA Trust anchor ☐ Exported
Controller Certs Signed by CA Controller auth ☐ Pending
WAN Edge Certs Signed by CA Device auth ☐ Pending
HTTPS Cert Public CA vManage UI ☐ Ordered

Enterprise CA Configuration Verification

# Verify CA certificate export
openssl x509 -in /etc/pki/ca-trust/source/anchors/abhavtech-root-ca.crt \
  -text -noout | grep -E "(Subject|Issuer|Not After)"

# Expected output:
# Subject: CN=Abhavtech-Root-CA, O=Abhavtech, C=IN
# Issuer: CN=Abhavtech-Root-CA, O=Abhavtech, C=IN
# Not After : Dec 31 23:59:59 2035 GMT

# Verify CA chain
openssl verify -CAfile abhavtech-root-ca.crt abhavtech-issuing-ca.crt

Firewall Rules Prerequisites

Source Destination Port Protocol Purpose Status
WAN Edge vBond 12346 UDP/DTLS Authentication ☐
WAN Edge vSmart 12346 UDP/DTLS OMP ☐
WAN Edge vManage 12346 UDP/DTLS Management ☐
WAN Edge WAN Edge 12346 UDP/DTLS IPsec IKE ☐
WAN Edge WAN Edge 12386 UDP BFD ☐
Admin vManage 443 TCP Web UI ☐
Admin vManage 8443 TCP API ☐
vManage SMTP 25/587 TCP Email alerts ☐
vManage NTP 123 UDP Time sync ☐
vManage DNS 53 UDP/TCP Resolution ☐

5.2.5 Integration Prerequisites

SD-Access Integration Readiness

Requirement Status Owner Notes
Border nodes identified ☐ LAN Team Mumbai: CAT-C9500-BN-½
VRF-Lite subinterfaces ready ☐ LAN Team Dot1Q encapsulation
BGP AS numbers assigned ☐ Architecture SD-Access: 65100, SD-WAN: 65200
Route-map filters defined ☐ LAN Team Prevent loops
CTS inline tagging enabled ☐ Security End-to-end SGT

SD-Access Border Configuration Verification

! Verify SD-Access border is ready for handoff
Border-Node# show vrf
  Name         Default RD     Protocols   Interfaces
  Employee     1:10           ipv4        Vlan10, Gi1/0/1.10
  Guest        1:20           ipv4        Vlan20, Gi1/0/1.20
  IoT          1:30           ipv4        Vlan30, Gi1/0/1.30
  Voice        1:40           ipv4        Vlan40, Gi1/0/1.40
  Shared       1:50           ipv4        Vlan50, Gi1/0/1.50

! Verify subinterface for WAN Edge handoff
Border-Node# show run interface GigabitEthernet1/0/1.10
  interface GigabitEthernet1/0/1.10
   encapsulation dot1Q 10
   vrf forwarding Employee
   ip address 172.16.1.1 255.255.255.252
   no shutdown

External System Integration

System Integration Type Purpose Status
ISE 3.3 RADIUS WAN Edge authentication ☐ Ready
Catalyst Center 2.3.7 REST API Unified management ☐ Pending
Infoblox IPAM API IP allocation ☐ Ready
Splunk Syslog Security analytics ☐ Pending
PagerDuty Webhook Alert escalation ☐ Pending
ServiceNow API ITSM integration ☐ Pending

5.2.6 Operational Prerequisites

Team Readiness

Role Training Required Status Certification
Network Engineers SD-WAN Operations ☐ CCNP SD-WAN
NOC Analysts SD-WAN Monitoring ☐ Internal
Security Team SD-WAN Security ☐ Internal
Helpdesk Basic Troubleshooting ☐ Internal

Documentation Readiness

Document Status Owner
High-Level Design ☐ Complete Architect
Low-Level Design ☐ In Progress Engineer
Runbook Draft ☐ In Progress Operations
Test Plan ☐ Complete QA
Rollback Procedures ☐ In Progress Engineer

5.2.7 Final Pre-Deployment Checklist

Go/No-Go Checklist

+------------------------------------------------------------------+
|              ABHAVTECH SD-WAN DEPLOYMENT GO/NO-GO                 |
+------------------------------------------------------------------+
|                                                                   |
|  Date: _______________    Phase: _______________                 |
|                                                                   |
|  INFRASTRUCTURE                                       Sign-off   |
|  ☐ All internet circuits tested and operational       _______    |
|  ☐ IP addresses allocated and verified                _______    |
|  ☐ DNS entries created and resolving                  _______    |
|  ☐ Firewall rules implemented and tested              _______    |
|                                                                   |
|  HARDWARE                                             Sign-off   |
|  ☐ All equipment received and inventoried             _______    |
|  ☐ Serial numbers match purchase orders               _______    |
|  ☐ Equipment staged at deployment locations           _______    |
|  ☐ Console access verified                            _______    |
|                                                                   |
|  SOFTWARE                                             Sign-off   |
|  ☐ Controller images downloaded                       _______    |
|  ☐ WAN Edge images downloaded                         _______    |
|  ☐ Licenses activated in Cisco Smart Account          _______    |
|  ☐ Security signatures updated                        _______    |
|                                                                   |
|  SECURITY                                             Sign-off   |
|  ☐ CA certificates exported                           _______    |
|  ☐ Certificate signing process documented             _______    |
|  ☐ Firewall rules tested                              _______    |
|  ☐ ISE integration ready                              _______    |
|                                                                   |
|  INTEGRATION                                          Sign-off   |
|  ☐ SD-Access border configuration validated           _______    |
|  ☐ BGP parameters agreed                              _______    |
|  ☐ External system APIs tested                        _______    |
|                                                                   |
|  OPERATIONAL                                          Sign-off   |
|  ☐ Team training completed                            _______    |
|  ☐ Documentation available                            _______    |
|  ☐ Escalation contacts confirmed                      _______    |
|  ☐ Change approval obtained                           _______    |
|                                                                   |
|  DECISION: ☐ GO   ☐ NO-GO                                        |
|                                                                   |
|  Approver: _________________  Date: _______________              |
|                                                                   |
+------------------------------------------------------------------+

Document Control

Version Date Author Changes
1.0 December 2025 Abhavtech Network Engineering Initial release

Abhavtech Confidential - SD-WAN Pre-Deployment Checklist